Illustrative examples
See the estimating workflow in practice
Six worked examples, one for each kind of output. Each follows an input through measurement, structure and review to the document it produces.
These are illustrative scenarios built on one sample building. They are not customer projects, and the sheets, references and figures are not real project data. Rates are named, never valued.
- EX-01Quantity TakeoffPlan A-101 → Quantity schedule
- EX-02BOQ PreparationSheets A-101 · A-301 → Bill of Quantities
- EX-03Construction Cost EstimatingBill items → Cost estimate
- EX-04Material TakeoffDetail A-310 → Material schedule
- EX-05Specialist EstimatingLayout M-101 → Package estimate
- EX-06Tender EstimatingTender set · T2 → Tender estimate pack
One sample building · every sheet illustrative
How to read an example
Input, process, output, review
Every example answers the same six questions, in the same order as the workflow.
Input
Drawing
Process
Measure · structure
Output
Document
Review
Checks
- Input
- The sheet or documents the example starts from, with their revision.
- Process
- What was identified, measured and structured — and who confirmed it.
- Output
- A page of the resulting document, with its references.
- Review
- The checks made before the output is issued.
EX-01 · Quantity Takeoff
A ground floor plan, measured into a quantity schedule
One plan sheet, taken off element by element, with every line pointing back to the sheet.
Input
Plan A-101
Process
Measurements
Output
Quantity schedule
Review
Review
- What was the input?
- Ground floor plan A-101 at Rev B, with the specification for the elements shown.
- What was identified?
- The external wall, the room floor, the skirting run and three door sets. AI-Assisted Drawing Intelligence highlighted candidates; the estimator confirmed each one.
- What was measured?
- Wall W-01 16.00 m; floor A-03 8.00 × 5.60 m = 44.80 m²; skirting F-01 27.20 m; doors D-01 to D-03, 3 nr.
- How was it structured?
- As dimension-sheet lines — times, dimensions, squared result and description — grouped by element, each with its sheet and revision.
- What output was produced?
- Quantity schedule QT-A101.
- What was reviewed?
- The scale on the sheet, the units, the door count against the plan, and the source on every line.
Output · Quantity schedule
| Times | Dimension | Squared | Description |
|---|---|---|---|
| W-01 · Grid 1 / A–D · A-101 Rev B | |||
| 1/ | 16.00 | 16.00 | External wall run · m |
| A-03 · A-101 Rev B | |||
| 1/ | 8.00 × 5.60 | 44.80 | Room floor area · m² |
| F-01 · A-101 Rev B | |||
| 2/ | 8.00 | 16.00 | Skirting, long walls |
| 2/ | 5.60 | 11.20 | Skirting, short walls |
| Σ | 27.20 | Skirting total · m | |
| D-01 · A-101 Rev B | |||
| 3/ | — | 3 | Internal doors · nr |
Review · checked before issue
- Scale confirmed on every sheet measured
- Unit matches the measurement type: m, m², m³ or nr
- Source sheet and revision on every line
- Counts re-checked against the drawing
- Unconfirmed suggestions kept out of the schedule
EX-02 · BOQ Preparation
A wall section and plan, structured into a bill of quantities
The same building, written up as described items under work sections.
Input
Sheets A-101 · A-301
Process
Work sections
Output
Bill of Quantities
Review
Validation
- What was the input?
- Wall section A-301 and plan A-101, both at Rev B, with the specification for the item descriptions.
- What was identified?
- The masonry, lintels, floor finish and skirting in scope, confirmed by the estimator.
- What was measured?
- Blockwork 16.00 × 2.60 m = 41.60 m²; lintels 3 nr; floor finish 44.80 m²; skirting 27.20 m.
- How was it structured?
- Two work sections — E Masonry and M Finishes — with items E.1–E.2 and M.1–M.2, each with a description, unit, quantity and sheet.
- What output was produced?
- Bill of Quantities BOQ-01.
- What was reviewed?
- Descriptions against the specification, units against the measurement type and references against the sheets.
Output · Bill of Quantities
| Item | Description | Unit | Qty | |
|---|---|---|---|---|
| E · Masonry | ||||
| E.1 | Blockwork wall, 100 mm, external wall W-01A-301 · Rev B | m² | 41.60 | |
| E.2 | Lintels over openingsA-301 · Rev B | nr | 3 | |
| M · Finishes | ||||
| M.1 | Floor finish to room A-03A-101 · Rev B | m² | 44.80 | |
| M.2 | Skirting to room A-03A-101 · Rev B | m | 27.20 | |
Review · checked before issue
- Every item has a description, unit and quantity
- Item references are unique and in sequence
- Descriptions match the specification
- Quantities traced to drawing sheets
- No work measured twice across sections
EX-03 · Construction Cost Estimating
A bill priced into a cost estimate, with the working shown
The bill items carried into an estimate, line by line, with named rates.
Input
Bill items
Process
Quantity × rate
Output
Cost estimate
Review
Validation
- What was the input?
- The measured items from BOQ-01 and the project's controlled rate set.
- What was identified?
- The rate in the controlled set that applies to each item, matched by unit.
- What was measured?
- Nothing new — the quantities carry through from the bill: 41.60 m², 3 nr, 44.80 m² and 27.20 m.
- How was it structured?
- Each line as quantity × named rate. Lines add up to the section E and M totals, and sections to the estimate.
- What output was produced?
- Cost estimate ES-01. Rates are named here, not valued.
- What was reviewed?
- Rate units against quantity units, the rate source on every line, and section totals against the estimate total.
Output · Cost estimate
| Item | Quantity | Rate | Cost |
|---|---|---|---|
| Section E | |||
| E.1 | 41.60 m² | rate E.1 | 41.60 × E.1 |
| E.2 | 3 nr | rate E.2 | 3 × E.2 |
| Σ section E | Σ E | ||
| Section M | |||
| M.1 | 44.80 m² | rate M.1 | 44.80 × M.1 |
| M.2 | 27.20 m | rate M.2 | 27.20 × M.2 |
| Σ section M | Σ M | ||
| Estimate total | Σ E + Σ M | ||
Review · checked before issue
- Unit of rate matches unit of quantity
- Every rate has a recorded source
- Every quantity has a source sheet
- Section totals reconcile to the estimate total
- Estimator review before issue
EX-04 · Material Takeoff
A wall build-up, listed as a material schedule
One construction detail read layer by layer, each material measured once in its own unit.
Input
Detail A-310
Process
Material layers
Output
Material schedule
Review
Review
- What was the input?
- Wall detail A-310 at Rev B, the specification and foundation sheet S-101.
- What was identified?
- Five materials — blockwork, insulation, lining board, damp-proof course and foundation concrete — each confirmed against the specification.
- What was measured?
- The wall layers at 41.60 m² each, 16.00 m of damp-proof course and 16.00 × 0.60 × 0.40 m = 3.84 m³ of concrete.
- How was it structured?
- Tagged BLK, INS, BRD, DPC and CON, and grouped into masonry, insulation and linings, and groundworks packages.
- What output was produced?
- Material schedule MS-01.
- What was reviewed?
- Layers for double-counting, the unit for each material, and the insulation change from Rev A to Rev B.
Output · Material schedule
| Tag | Material | Unit | Qty | |
|---|---|---|---|---|
| Package · Masonry | ||||
| BLK | Blockwork, 100 mmA-310 | m² | 41.60 | |
| DPC | Damp-proof courseA-310 | m | 16.00 | |
| Package · Insulation and linings | ||||
| INS | Insulation, 100 mm · Rev BA-310 | m² | 41.60 | |
| BRD | Lining board, 12.5 mmA-310 | m² | 41.60 | |
| Package · Groundworks | ||||
| CON | Foundation concrete · 16.00 × 0.60 × 0.40S-101 | m³ | 3.84 | |
Review · checked before issue
- Each material confirmed against the specification
- Unit suits the material
- Layers measured once, not double-counted
- Drawing reference on every line
- Schedule reviewed before issue
EX-05 · Specialist Estimating
A ventilation layout, measured as a specialist package
A discipline drawing measured on its own terms, inside a scope boundary stated first.
Input
Layout M-101
Process
Scope boundary
Output
Package estimate
Review
Specialist review
- What was the input?
- Ventilation layout M-101 at Rev B and its equipment schedule.
- What was identified?
- The ductwork, bends, grilles and dampers inside the package boundary, and the air handling unit as by others.
- What was measured?
- Straight ductwork 42.50 m; bends 5 nr, supply grilles 8 nr and volume dampers 4 nr, counted from the layout.
- How was it structured?
- Package M lines DU-01, DU-02, GR-01 and DA-01, each marked in scope, with the by-others item listed and not priced.
- What output was produced?
- Package estimate PK-01.
- What was reviewed?
- Runs and counts against the layout, and the package against its stated boundary.
Output · Package estimate
| Ref | Item | Qty | Scope | |
|---|---|---|---|---|
| Package M · Ventilation · M-101 Rev B | ||||
| DU-01 | Ductwork, straight | 42.50m | In | |
| DU-02 | Bends | 5nr | In | |
| GR-01 | Supply grilles | 8nr | In | |
| DA-01 | Volume dampers | 4nr | In | |
| — | Air handling unit and plant connection | — | By others | |
Review · checked before issue
- Scope boundary recorded on the drawing
- By-others items listed, not priced
- Runs and counts checked against the layout
- Unit suits each component
- Package reviewed before issue
EX-06 · Tender Estimating
A tender drawing set, prepared with its queries and assumptions
A tender set registered, questioned and estimated, with the basis written down.
Input
Tender set · T2
Process
Queries & assumptions
Output
Tender estimate pack
Review
Final review
- What was the input?
- The tender drawing set at issue T2, including Addendum 01, with the tender documents.
- What was identified?
- Three gaps in the information, raised as queries Q-01 to Q-03.
- What was measured?
- Quantities from issue T2. Sheets revised by Addendum 01 were compared, and affected quantities re-measured.
- How was it structured?
- A six-section pack — register, scope review, quantities, estimate, queries and assumptions — with the query log kept current.
- What output was produced?
- Tender estimate pack TD-01.
- What was reviewed?
- The pack as a whole: open queries listed with their status, and assumptions and exclusions recorded.
Output · Tender estimate pack
| Ref | Query | Status | |
|---|---|---|---|
| Query and clarification log | |||
| Q-01 | Room height not dimensionedA-101 | Answered | |
| Q-02 | Lintel detail not shownA-301 | Open | |
| Q-03 | Corridor finish not scheduledA-101 | Open | |
Assumptions and exclusions
- A-04Typical lintel detail assumed until Q-02 is answered.
- A-05Quantities measured from issue T2 (Addendum 01).
- X-01Air handling unit and plant connection excluded — by others.
Review · checked before issue
- Every sheet in the register reviewed
- Open queries listed with their status
- Addenda checked against the quantities
- Assumptions and exclusions recorded
- Final review before the pack is issued
From example to project
The same workflow, on your own drawings
See each stage of the workflow in more depth, or compare the seven services to find the output your project needs.