Skip to content

Service 07 / 07

Tender Estimating

Quantities and estimates prepared to support a tender submission. The work runs from the tender drawing set through scope review, queries and recorded assumptions to a final review.

Output
Tender estimate pack
Workflow
Covers Drawing, Intelligence, Takeoff, BOQ, Estimate, then human review.
TD-01 · Tender drawing set · register · Issue T2Illustrative Example
Illustrative tender drawing set: stacked sheets A-101, A-301, S-101 and M-101, a query Q-01 clouded on the ground floor plan, addendum 01 revising A-101 from issue T1 to T2, and a drawing register showing each sheet's state.M-101S-101A-301A-101GROUND PLANISSUE T2TENDER SETQ-01ADDENDUM 01A-101T1 → T2T2REGISTERA-101T2A-301QS-101✓M-101✓Q = QUERY RAISED

Tender pack

Tender pack (illustrative)
No.SectionState
01Drawing registerComplete
02Scope reviewComplete
03QuantitiesReviewed
04EstimateIn review
05Queries2 open
06AssumptionsRecorded

Final review before submission

What it does

Quantities, an estimate and a stated scope for the tender

Tender estimating prepares the quantities and estimate a submission needs. The scope is reviewed first, so gaps and ambiguities are raised early as queries.

Assumptions and exclusions are recorded with the estimate, so the basis of the submission is stated, not implied.

SETTender drawing set
Registered by sheet and revision
SCOPEScope review
Gaps found before measurement
QTYQuantities
Measured from the tender drawings
ΣEstimate
Built up from quantities and controlled rates
QQueries
Ambiguities raised as clarification queries
A / EAssumptions and exclusions
The basis of the estimate, written down

Inputs

What we work from

The project's own documents. Core inputs are needed for this service; the others are used where the project has them.

  • Tender drawings

    Core

    The issued tender drawing set.

  • Specifications

    Core

    Defines the work being tendered.

  • Tender documents

    Core

    Instructions and any pricing documents issued.

  • Schedules

    Where relevant

    Doors, windows and finishes.

  • Addenda

    Where relevant

    Revised information issued during the tender.

Workflow

A tender workflow with the scope stated

Queries and assumptions are part of the workflow, not an afterthought, so the submission says what it is based on.

  • Estimator
  • AI-assisted suggestion
  • Controlled calculation
  • Human review
  1. 01

    Drawing

    Register the tender set

    Every sheet and document is listed with its issue.

    Who: Estimator

  2. 02

    Drawing

    Review the scope

    Gaps and ambiguities are raised as queries.

    Who: Estimator

  3. 03

    Takeoff

    Extract quantities

    AI-Assisted Drawing Intelligence can suggest elements. The estimator confirms and measures.

    Who: Estimator

  4. 04

    Estimate

    Build the estimate

    Quantities are priced with controlled rates by section.

    Who: Estimator

  5. 05

    Estimate

    Record the basis

    Assumptions, exclusions and query answers are recorded with the estimate.

    Who: Estimator

  6. 06

    Review

    Final review

    The pack is reviewed as a whole before it is issued.

    Who: Human review

Deliverable

Tender estimate pack

The pack index, with the query log and the assumptions recorded alongside the estimate.

Every output includes

  • Drawing register
  • Quantities and estimate
  • Query and clarification log
  • Assumptions and exclusions
TD-01Tender estimate pack
Illustrative Example
Illustrative tender query log
RefQueryStatus
Query and clarification log
Q-01Room height not dimensionedA-101Answered
Q-02Lintel detail not shownA-301Open
Q-03Corridor finish not scheduledA-101Open

Assumptions and exclusions

  • A-04Typical lintel detail assumed until Q-02 is answered.
  • A-05Quantities measured from issue T2 (Addendum 01).
  • X-01Air handling unit and plant connection excluded — by others.
Illustrative Example — not a real projectSheet 1 of 1

Checked and traceable

The basis of the tender, written down

A final review checks the pack as a whole: drawings, quantities, estimate, queries and assumptions.

Checked before issue

  1. 01Every sheet in the register reviewed
  2. 02Open queries listed with their status
  3. 03Addenda checked against the quantities
  4. 04Assumptions and exclusions recorded
  5. 05Final review before the pack is issued

One line followed back to its source, and one drawing revision handled. Neither is real project data.

Illustrative Example
Trace · query Q-02
  1. Query

    Q-02 · Lintel detail not shown

  2. Sheet

    A-301 · Wall section · T1

  3. Item

    E.2 · Lintels · 3 nr

  4. Assumption

    A-04 · Typical detail assumed

  5. Pack section

    05 · Queries

  6. State

    Open

Revision · Addendum 01

Was A-101 · Issue T1

changed to A-101 · Issue T2

Revised sheets are compared, affected quantities re-measured and the register updated.

Tender Estimating

Prepare the tender with its scope stated

Compare the seven services, or see how the full workflow moves from the drawings to a reviewed estimate.

Related services

  • Output · Cost estimate

    Construction Cost Estimating

    Cost estimates built up from measured quantities and explicit rates, with the calculation inputs kept visible for review.

  • Output · Bill of Quantities

    BOQ Preparation

    Bills of Quantities structured into work sections, with clear item descriptions, units and quantities.

  • Output · Trade-structured estimate

    Commercial Estimating

    Estimating for commercial building projects, structured by trade and work section.